Thursday, March 30, 2023

31 MAR 23 HKL

 

NSC GROUP
 Azman HKL: Good morning. 31/03/2023.

Site progress picture.
6th floor. Column rebar and closure in progress.
 Azman HKL: Zone 1&2. 1st floor. Slab formwork and beam rebar in progress.
Azman HKL: Zone D/a. Ramp 3 formwork in progress. 1st floor. Column rebar in progress. 2nd floor scaffolding support in progress.
Azman HKL: Zone 2&3.  Basement foundation cast. Rebar in progress.
 Azman HKL: GL: I-L/11-14. Basement foundation in progress.
 Lo. W. H (HKL-Site Engineer): @Edwin Chen 013 @KH SU YEE CHONG
 Lo. W. H (HKL-Site Engineer): please check back the toilet at 2nd floor ..should there any obstruction to your services
 Lo. W. H (HKL-Site Engineer): please highlight to me
Azman HKL: @Leung KH🍀 when can continue to lift this FRP? Any obstruction?
 Azman HKL: Ground floor. Casting plan. Zone 11. 8/04/2023
Azman HKL: Casting plan. 1st floor. Zone 4. 5/04/2023