SITE GROUP
Azman HKL: Good morning.
29/03/2023. Site pic progress.
6th floor column closure in progress.
Azman HKL: Zone 7a. Basement slab cast.
Azman HKL: Zone 1&2. 1st floor slab formwork in progress.
Azman HKL: Ramp 2.
Azman HKL: Basement foundation GL: I-L/11-14. Earthwork in progress.
Azman HKL: Zone 2B/a. Ramp 3 & 2nd floor support scaffolding in progress.
Azman HKL: Zone 2D/b. Slab rebar and conduit work in progress.
Azman HKL: @Kadapi J. HKL RFI, 1st floor slab GL: I-L/8-11 at 1.30pm.
Kadapi J. HKL: Boleh bah klu kau.
NSC GROUP
Mr. Voo: @Azman HKL kasih atur diaorng pindah ni
Mr. Voo: Pg sini dulu tapi lapis ni slab
Mr. Voo: Tc2 sya terlalu senang skrg sampai operator tido tido sdh
Azman HKL: @Leung KH🍀 @Edwin Chen 013 please arrange by today. Can use TC2. Operator tido2 tunggu sini..
Mr. Voo: Plz bare in mind , we arrange the machine but not machine arrange us !!
Azman HKL: 💪
Lo. W. H (HKL-Site Engineer): @~Liaw Ka Pang @~YoonYK
Lo. W. H (HKL-Site Engineer): relocation of escalator as per clouded
Lo. W. H (HKL-Site Engineer): please take note
Lo. W. H (HKL-Site Engineer): @Azman HKL
+60 12-843 3877: ElE&Elv ready for insfection
Azman HKL: 1st floor slab. M&E inspection done 👍