SITE GROUP
Azman HKL: Good morning.
20/03/2023. Site progress.
6th floor. Column.
Azman HKL: 1st floor. Slab formwork in progress.
Azman HKL: 1st floor. Slab formwork & beam rebar in progress.
Azman HKL: Basement foundation. Zone 2&3. Slab beam rebar in progress. Watertank plinth in progress.
Azman HKL: ST8. Rebar and M&E conduit in progress.
NSC GROUP