Tuesday, March 14, 2023

15 MAR 23 HKL

NSC GROUP

Azman HKL: Good morning. 
Site progress. 15/03/23.
Ramp2 casted.
Azman HKL: 1st floor. Formwork inprogress.
Azman HKL: Zone 1D/b. Column in progress.
Azman HKL: Zone 2&3. Basement foundation. Rebar in progress.
 Azman HKL: Ground floor. Staircase 7 rebar in progress.
 Azman HKL: GL: E-F/7-10. Basement rebar foundation in progress.








 