04 MAR 23 HKL

NSC GROUP

Azman HKL: Good morning.
4/3/2023. Site progress.
6th floor. Column casted. Column rebar in progress.
Azman HKL: 6th floor column rebar in progress.
 Azman HKL: Zone 2&3. Basement foundation rebar in progress.
Azman HKL: Zone 1&2. Ground floor. Column rebar in progress.
Azman HKL: Zone 1D/a. 1st floor. Slab rebar. M&E services in progress.
Azman HKL: Zone 1D/b. Ground floor. Beam rebar in progress.
 Azman HKL: Predestrian ramp slab rebar in progress.




Azman HKL: Zone 6. Casting postponed to 6/3/23. Monday. All NSC. PIC in site  please take note. 🙏




Azman HKL: Zone 1D/d. Ground floor. Slab rebar in progress. Casting plan on Monday.
Azman HKL: KH pipe sleeve installation in progress..


















 