Thursday, March 2, 2023

03 MAR 23 HKL

SITE GROUP

Azman HKL: Good morning.. 
3/3/23. Site progress.
6th floor. Column rebar in progress.
Azman HKL: Zone 1&2. Ground floor. Column rebar and closure.
Azman HKL: Zone 1D/a. 1st floor. Slab rebar. M&E services in progress.
Azman HKL: Zone 1D/b. Ground floor. Beam rebar in progress. Ramp 2. Slab rebar in progress.




NSC GROUP

 Azman HKL: This ground floor casting plan is on Sunday. Subcon will get it ready for M&E installation by tomorrow morning. @shawnstchia @DartWeirdo 🇲🇾 @ @Leung KH🍀 please get it ready for tomorrow. Any obstruction please inform us early. 🙏🙏🙏
+60 16-837 8881: Noted
 Azman HKL: 🤲🏻
Azman HKL: Heavy rain..











 