Azman HKL: @Leppong please check if bottom rebar done, conduit can start. Target casting tomorrow.🙏
[10:58, 02/03/2023] +60 17-866 0355: Ok man
Azman HKL: Please be informed. Casting plan ground floor and ramp 5 at GL: I-L/7-11 on 05/03/2023
Azman HKL: Conduit at ramp 2 in progress.
Azman HKL: 2/03/23. Site progress.
6th floor. Column in progress.
Azman HKL: Basement. Zone 2&3 earthwork & foundation work in progress.
Azman HKL: Ground floor. Column in progress.
Azman HKL: zone 1D/a . 1st floor. Slab M&E services in progress. Ramp2 slab rebar in progress.
Azman HKL: Ground floor. Zone 1D/b. Slab rebar in progress.