Friday, March 31, 2023

01 APR 23 HKL

NSC GROUP

Azman HKL: Good morning. 01/04/2023.
Site picture progress.
6th floor. column closure in progress.
Azman HKL: Zone 4. 1st floor. Beam rebar and formwork in progress.
 Azman HKL: 1st floor. Column rebar and 2nd floor scaffolding support in progress.
 Azman HKL: 1st floor. Ramp3 formwork and column rebar in progress.
Azman HKL: Zone 2 & zone 3. Basement foundation. Floor slab cast. Slab rebar in progress.
Azman HKL: Zone 7a. Column rebar in progress.
Azman HKL: DCC on site runs conduit in column.💪

Raymond Chong. Y. F (HKL P. Manager): @+60 14-969 5997 @+60 19-775 6210 @+60 12-802 6369
@Azman HKL  1st floor zone 4 target casting on 4/4/2023(tuesday)
Azman HKL: @Edwin Chen 013 @Leung KH🍀 @KH Karen please can lift this FRP to the temporary storage by today. Subcon will install column here. 🙏🙏🙏🙏🙏🙏🙏🙏🙏🙏
 Azman HKL: @~Leppong @~. @~ShawnChia @~Walker Yapp @~DartWeirdo 🇲🇾 @Leung KH🍀 please take note. Check & plan your services to install. Any obstruction informs and manage early.
[08:43, 01/04/2023] +60 16-837 8881: Noted
 Azman HKL: Zone 5a. Basement foundation. Bore pile work in progress.
[08:46, 01/04/2023] Mr. Voo: Sini ada earthing kah ?
[08:46, 01/04/2023] +60 17-866 0355: ya ada
 Mr. Voo: Ok .. lepas leancon kasih boom dia ya 🙏🏻
 Azman HKL: Wayar ini masi pakai ka?ada⚡⚡ka in? Nanti sot mati org oh..tolong cabut..tq🙏🏻
Azman HKL: @~Leppong tolong nanti gulung baik2. Nanti ada sot mati org.. 💀
+60 16-837 8881: Ni tiada current , nanti kami gurung
 Azman HKL: TQ.

 Azman HKL: Zone 2. Column in progress.
 Azman HKL: Zone 7a column in progress.
Azman HKL: 1st floor. Column in progress.
 Azman HKL: Basement GL: I-L/11-14. Basement foundation.
































 

01 APR 23










 

Thursday, March 30, 2023

31 MAR 23 HKL

 

NSC GROUP
 Azman HKL: Good morning. 31/03/2023.

Site progress picture.
6th floor. Column rebar and closure in progress.
 Azman HKL: Zone 1&2. 1st floor. Slab formwork and beam rebar in progress.
Azman HKL: Zone D/a. Ramp 3 formwork in progress. 1st floor. Column rebar in progress. 2nd floor scaffolding support in progress.
Azman HKL: Zone 2&3.  Basement foundation cast. Rebar in progress.
 Azman HKL: GL: I-L/11-14. Basement foundation in progress.
 Lo. W. H (HKL-Site Engineer): @Edwin Chen 013 @KH SU YEE CHONG
 Lo. W. H (HKL-Site Engineer): please check back the toilet at 2nd floor ..should there any obstruction to your services
 Lo. W. H (HKL-Site Engineer): please highlight to me
Azman HKL: @Leung KH🍀 when can continue to lift this FRP? Any obstruction?
 Azman HKL: Ground floor. Casting plan. Zone 11. 8/04/2023
Azman HKL: Casting plan. 1st floor. Zone 4. 5/04/2023













31 MAR 23





 

Wednesday, March 29, 2023

30 MAR 23 HKL

SITE GROUP

Azman HKL: Good morning. 
30/03/2023. Site progress pic.
6th floor. Column closure in progress.
Azman HKL: 1st floor. GL: J-L/1-4. Beam rebar & formwork in progress.
Azman HKL: 1st floor slab. GL: I-L/8-11.  Slab cast.
 Azman HKL: Basement foundation. GL: I-L/11-14. Earthwork in progress.
Azman HKL: Basement foundation. Zone 7a.
Azman HKL: Zone 2&3. Basement foundation. Rebar and post tension in progress.

 Azman HKL: Dear all.. please take note of this area..Basement foundation. GL: I-L/12-14. double check any item so we do not miss out. Water tank plinth, pump sump pit. BL lift pit. Please advise if any. Thanks.

 Azman HKL: Basement foundation in progress.

NSC GROUP
Azman HKL: Lifting FRP water tank to basement.
 Mr. Voo: 👍🏻















 

30 MAR 23





































 

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...