SITE GROUP
Azman HKL: Good morning.
Site progress. 25/02/2023. 6th floor. Column rebar and formwork in progress.
Azman HKL: 6th floor. Zone 2. Slab casted.
Azman HKL: Ground floor. Zone 1D. slab formwork in progress. 1st floor. Slab formwork and lift formwork in progress.
Azman HKL: Basement. Zone 2&3. Earthwork in progress. Ground floor, Zone 1&2. Column rebar in progress.
Azman HKL: Basement. Zone 1D. Predestrian ramp formwork in progress.
Azman HKL: Basement. Slab formwork in progress.
NSC GROUP