Friday, February 24, 2023

24 FEB 23 HKL

NSC GROUP 


Azman HKL: Good morning. To inform to all. Site tower crane usage is very demanding. Priority is to  building construction so most work can mobilize. So please be patient with our Signalman and TC operator. 🙏they have working nonstop to mobilize material as per requested.
Azman HKL: TC2 just started operating yesterday after JKKP approval and additional signalman is coming today.
Azman HKL: TC2 this morning is available.
Azman HKL: @Walker Yapp @DartWeirdo 🇲🇾 your services?.. Now inspection in progress.. 🙏🙏🙏
+60 16-801 0751: Otw
Azman HKL: Sda ada🫰
Azman HKL: Good morning. 
Site progress. 24/02/2023.
6th floor. Column rebar and closure in progress.
Azman HKL: 6th floor slab rebar n M&E done inspection.
Azman HKL: 6th floor slab Join inspection M&E services.
Azman HKL: 1st floor. Slab formwork and lift formwork in progress.
 Azman HKL: Basement. Zone 1D. Ground floor formwork in progress.
 Azman HKL: Basement pedestrian ramp formwork in progress
Azman HKL: Water tank FRP in site.

KH Karen: @Azman HKL @Raymond Chong. Y. F (HKL P. Manager) @Mr. Voo 
tomorrow morning 9am,we need your kind assist of mobile crane and tower crane to move our tank materials to basement near tank area.
we will have 3 workers standby on site.
Thank you.
Raymond Chong. Y. F (HKL P. Manager): Have u studied the location where to hoist and stored? 3 workers enough? How many hours u required? FYI our mobile crane is not just serving u but for other hoisting as well ya
Raymond Chong. Y. F (HKL P. Manager): @KH Karen who is your supervisor at site for coordination?
 Edwin Chen 013: Yes. We already started yesterday to the location that we wanted.
 Edwin Chen 013: Leung
Raymond Chong. Y. F (HKL P. Manager): Please get Leung to see me tomorrow morning