Azman HKL: Good morning.
Site progress. 23/02/2023
6th floor. Column rebar in progress
Azman HKL: 6th floor. Slab rebar n M&E services in progress.
Azman HKL: DCC worker installing conduit in progress.
Azman HKL: 1st floor slab. Zone 1D formwork in progress.
Azman HKL: Basement zone 2&3. Earthwork in progress
NSC GROUP
Azman HKL: Morning. Bottom rebar installed. Please proceed to M&E services this morning. π. @. @Leung KHπ @Walker Yapp.
+60 16-837 8881: ππ»
Azman HKL: @EG Mall Kin Hong Site Coord Chong SY if can please come early. πππIni mobile crane ramai maw book angkat barang. Nanti ah @Raymond Chong. Y. F (HKL P. Manager) @Mr. Voo bising saya lagi.
KH SU YEE CHONG: noted, thanks
Azman HKL: JKKP in site.π
Azman HKL: FRP water tank loading in progress.
Azman HKL: Electrical conduit in progress.