20 FEB 23 HKL

SITE GROUP

 Azman HKL: Good morning.
20/02/2023. 
6th floor. Casted.
Azman HKL: 6th floor. Slab formwork and rebar beam in progress.
Azman HKL: Basement. Zone 2&3. Earthwork in progress.
Azman HKL: Zone 1. 1st floor slab formwork in progress.
Azman HKL: Basement housekeeping for water tank FRP material arrival and storage.
Azman HKL: Basement retaining wall  closure in progress




 