Azman HKL: Good morning. 18/02/2023
Site progress. 
6th floor casted.
Azman HKL: 6th floor. Formwork & rebar in progress.
Azman HKL: Basement. Column rebar and closure in progress. Retaining wall rebar and formwork in progress.
Azman HKL: 1st floor. Slab formwork in progress.
Azman HKL: Basement zone 2&3. Earthwork in progress.



 