Thursday, February 16, 2023

17 FEB 23 HKL

SITE GROUP

Azman HKL: Good Morning. 
Site progress. 17/02/2023
6th floor slab. Slab cleaning before casting in progress.
Azman HKL: 6th floor. Slab formwork in progress.
Azman HKL: Basement. Zone 2&3. Earthwork in progress.
Azman HKL: 1st floor. Zone 1. Slab formwork in progress.
 Azman HKL: Basement. Zone 1D. Retaining wall formwork in progress. Column formwork in progress to close. Sanitary CI pipe and cable pipe sleeve installed.
Azman HKL: Lift pit wall formwork closure in progress.
Azman HKL: Mroning bossku. @⁨Kadap@Kadapi J. HKL Request for inspection 6th floor slab pagi ini. 🙏.
Kadapi J. HKL: Boleh bah klu kau. Saya naik atas sekarang. Prepare drawing ya.
Azman HKL: 👌






 