Azman HKL: Good morning.
Site progress. 14/02/2023.
6th floor. Partially slab bottom bar installed. Slab bottom rebar in progress.
Azman HKL: 6th floor. Slab formwork and rebar in progress
Azman HKL: Basement retaining wall rebar in progress.
Azman HKL: Basement retaining wall rebar. GL: L/8-11.
Azman HKL: 1st floor slab. Zone 1. Slab formwork in progress. Ground floor lift pit wall in progress.
Azman HKL: Ground floor zone 1. Earthwork in progress
Azman HKL: Basement zone 2&3. Earthwork in progress.
Azman HKL: DCC workers on the 6th floor to install conduit at slab.
Kadapi J. HKL: 6th floor not yet ready for conduit installation. 🤔
Kadapi J. HKL: Bar bander to speed up a bit lahhh🙂
Azman HKL: Today M&E Coordination meeting. 3.00pm.