13 FEB 23 HKL

SITE GROUP
Azman HKL:Good morning.
13/02/2023. Site progress.
6th floor. Slab rebar in progress.
Azman HKL: 6th floor. Slab formwork in progress
Azman HKL: 6th floor rebar installation
Azman HKL: Basement. Zone 2&3 earthwork in progress
Azman HKL: Ground floor. Zone 1&2.  Column rebar in progress
Azman HKL: Ground floor, lift pit formwork and rebar in progress. 1st floor slab formwork in progress.
Azman HKL: Basement. Zone 1D. Column revar in progress.
Azman HKL: Lift pit rebar in progress
 Azman HKL: Wall rebar in progress. Any pipe sleeve thru wall please check and study. Casting plan this wednesday.🙏👆







 