SITE GROUP
Azman HKL: Good morning.
9/02/2023.
6th floor. Slab form work and beam rebar.
Azman HKL: 6th floor. Slab, escalator opening formwork.
Azman HKL: 6th floor. Slab formwork in progress.
Azman HKL: Basement. Zone 2&3. Earthwork in progress
Azman HKL: Ground floor. Slab casted.
Azman HKL: Ground floor. Zone 1D. Lift pit formwork in progress. Column in progress.
Azman HKL: Basement. Zone 1D. Slab rebar in progress
Azman HKL: @Kadapi J. HKL done install earthing services at basement. Ready for another inspection.
Kadapi J. HKL: Ok im coming
Azman HKL: Floor trap from riser room, discharge to scupper drain. As per shop drawing. Waiting for the subcon to install the scupper drain.
NSC GROUP
Azman HKL: Joint Inspection for M&E services at the basement floor.
Azman HKL: Install piping at the slab.