Monday, February 6, 2023

07 FEB 23 HKL

SITE GROUP

Azman HKL: Good morning. 7/2/2023
Site progress. 6th floor. Slab formwork and rebar in progress
Azman HKL: Ground floor. Zone 1D. Column rebar and lift pit formwork in progress.
Azman HKL: Basement. Zone 1D. Slab rebar. Casting plan tomorrow. Please double check all M&E services in basement slab.
Azman HKL: Basement. Zone 2 & 3 earthwork i. Progress.
Azman HKL: Ground floor. Zone 1&2. Slab rebar and M&E services in progress.









NSC GROUP
Azman HKL: Consultant inspection on site.
Azman HKL: Reminder. Please make it ready to inspect all M&E services before 12pm. We plan to RFI at 1pm. Any obstruction please inform if needed so we  can handle it ASAP. Your cooperation is very appreciated. ๐Ÿ™๐Ÿ™๐Ÿ™๐Ÿซฐ
Azman HKL: @Leung KH๐Ÿ€ please check again all pipe sleeve, opening or boxes on site before inspection๐Ÿ‘†make sure all are in good condition.
Leung KH๐Ÿ€: Noted๐Ÿ™๐Ÿป
Azman HKL: Subcon will install the beam rebar here. ๐Ÿ‘†
+60 12-843 3877: Can not install pvcconduit yet
Leung KH๐Ÿ€: Cannot install pipe yet



Azman HKL: @LO KEAM Bro. Please send the softcopy of that shopdrawing by this week so we can proceed.
+60 19-895 9900: Bukan sdh meh?
Raymond Chong. Y. F (HKL P. Manager): @. ๐Ÿ‘†
Azman HKL: Okay. Just received. Thanks a lot. ๐Ÿซฐ
Raymond Chong. Y. F (HKL P. Manager): This area casting postponed to Thursday
Azman HKL: Raining on site.





 