Friday, January 20, 2023

21 JAN 23 HKL



SITE GROUP
Azman HKL: Good morning.. 
Site progress 21/01/2023.
5th floor. 6th floor beam formwork in progress.
Azman HKL: Basement. Zone 1D. Lift pit formwork closure in progress. Ground floor slab and beam rebar formwork in progress.
Azman HKL: Basement. Zone 1D. Pile cap L/10 rebar and formwork closure in progress.
Azman HKL: Basement zone 2A/a. Foundation rebar in progress. Lightning services test and installation in progress
Azman HKL: Install lightning services.









 