Thursday, January 19, 2023

20 JAN 23 HKL

SITE GROUP
Azman HKL: Morning. Site progress 20/01/2023. 5th floor. Column in progress.
Azman HKL: 5th floor column.
 Azman HKL: Basement. Zone 1D. Pile cap foundation rebar in progress.
Azman HKL: Basement. Lift pit wall in progress. Ground floor slab formwork in progress.
Azman HKL: Lift pit formwork and rebar.
Azman HKL: Pile cap L/10 foundation rebar
 Azman HKL: Basement column & ground floor slab formwork in progress
Azman HKL: Basement pile cap zone 2A/a. Rebar in progress.















 