Azman HKL: Site progress. 19/01/2023.
5th floor. Column rebar in progress
Azman HKL: Basement. Zone 1D. Lift pit rebar and formwork in progress. Pile cap K/10 & L/9 casted. Pile cap K/11, L/10 & L/11 foundation leancon & rebar in progress.
Azman HKL: Basement zone 2A/a leancon. Zone 2B earthwork in progress.
Azman HKL: Basement. Column rebar and formwork in progress. Ground floor slab form work in progress.
Azman HKL: Basement. Lift pit wall formwork and rebar in progress.
Azman HKL: Ground floor formwork and rebar in progress.