Azman HKL: Good morning.
18/01/2023. Site progress.
Basement zone 1D. Wall casted. Lift wall wall rebar in progress. Ground floor slab in progress.
Azman HKL: Basement. Foundation. Pile cap K/10 & L/9 rebar and formwork in progress. Pile cap L/10, K/11, L/11 in progress.
Azman HKL: Basement zone 2. Lean con in progress. Earthwork also in progress. Column closure work in progress
Azman HKL: Ground floor slab above water tank area formwork in progress
Azman HKL: Ground floor slab formwork in progress.