Sunday, January 15, 2023

16 JAN 23 HKL

SITE GROUP
Azman HKL: Pipe sleeve at basement wall to MH4. @Leung KH🍀 share your picture picture after work complete bah.. 🙏
Azman HKL: @Leung KH🍀 👆ok sda kan. Boleh invite @Kadapi J. HKL inspection ini jam 9am..
Leung KH🍀: Morning , yes 🙏🏻
Kadapi J. HKL: Lambat sikit datang. C ni masih gerimis.
Azman HKL: Ok. Masih gerimis lagi. Sy stanby sini GF.
Azman HKL: Site progress. 16/01/2023
5th floor. Column in progress.
Azman HKL: Basement, wall formwork, lift pit formwork & rebar, basement column and ground floor slab in progress.
Azman HKL: Basement wall rebar and formwork.
Azman HKL: Basement earthwork and cutting pile cap in progress
 Azman HKL: Basement zone 2. Column closure in progress.
 Azman HKL: Basement. Zone 3. Earthwork in progress.
Azman HKL: Basement TC 2 rebar in progress
 Azman HKL: M&E services inspection at basement wall, zone 1D.

















 