Tuesday, November 29, 2022

30 NOV 22 HKL

SITE GROUP
Azman HKL: Site progress. 30/11/2022 3rd floor column in progress

Azman HKL: Socket installation in column

Azman HKL: 3rd floor slab rebar, slab formwork inprogres
Azman HKL: Rebar inprogress



Azman HKL: Basement watertank. Column rebar, wall rebar, earthing cable work, plinth inprogress.

Azman HKL: Socket in Column I/5

Azman HKL: Gl: F-I/8-10. Bottom rebar inprogres. Conduit installation inprogress.









NSC GROUP
Azman HKL: F/5, done installation and got approval from consultant.

videos from Raymond Chong. Y.F (HKL P. Manager)





 