SITE GROUP
Azman HKL: Site progress, 29/11/2022. 3rd floor column inprogress
Azman HKL: Morning.. NSCs, 3rd floor. Tolong cek drawing column services. Formwork tutup hari ini.👆
Azman HKL: 3rd floor
Azman HKL: 3rd floor slab and rebar
Azman HKL: Basement water tank. Column inprogress
Azman HKL: Pile cap area
Azman HKL: Escalator opening.
Azman HKL: Technical meeting. M&E services at basement
NSC GROUP
Azman HKL: I/6
Azman HKL: G/6
Azman HKL: Slab
Azman HKL: HKL, Econmech, KH, DCC, consultant PIC.