SITE GROUP
Azman HKL: Good morning. Site progress. 21/11/2022. 3rd floor slab. Formwork and beam rebar
Azman HKL: Also @. @shawnstchia @Joseph Wong KH @DartWeirdo 🇲🇾 check for drawing 3rd floor. Casting plan 25/11/2022. M&E should start on 22-23.
Azman HKL: 2nd floor columnAzman HKL: Also @. @shawnstchia @Joseph Wong KH @DartWeirdo 🇲🇾 check for drawing 3rd floor. Casting plan 25/11/2022. M&E should start on 22-23.
Azman HKL: Basement watertank GL: K-L/3-4 column. 👆earthing.
Azman HKL: GL: K/9. Earthing👆
Kadapi HKL: 😳 earthing havent joint yet?
Azman HKL: @. RFI 👆
Azman HKL: Basement wall.
Azman HKL: Lighting point conceal for ramp if any..
Azman HKL: Lighting point conceal for ramp if any..
Azman HKL: GL: F-I/10-11. Please double check if any conduit to conceal in column. I cant check no latest drawing. 👆
Azman HKL: @Yoon YK can arrange to come on tommorow to check escalator pit opening.
Kadapi : Cable joint not acceptable. Please redo the joint again b 4 they cast the pile cap. Tq
Azman HKL: Joint inspection GL: K/9. Earthing installation.