Azman HKL: Site progress. 21/12/2022
4th floor slab. Done casting.
Azman HKL: 5th floor slab and beam formwork inprogress.
Azman HKL: Basement. Zone 2. Raft foundation rebar in progress. GL: K/1-4 wall in progress
Azman HKL: Basement zone 1D. Earthwork for pile cap in progress.
Azman HKL: @shawnstchia plan the exothermic lightning point base on site condition. The bottom rebar is in progress. 👆