19 DEC 22 HKL

SITE GROUP

Azman HKL: Site progress. 19/12/2022
4th slab rebar inprogress.

Azman HKL:  Column & beam rebar inprogress.
Azman HKL:  Basement water tank wall in progress. Zone 2, earthwork rebar inprogress.

Azman HKL:  Zone 1D, earthwork in progress.




Azman HKL:  Pipe sleeve at basement wall inspection.

Azman HKL:  Wall inspection with approval.

 