SITE GROUP
Azman HKL: Site progress. 14/12/2022 4th floor slab. Formwork inprogress.
Azman HKL: Basement watertank inprogress
Azman HKL: Zone 2. Earthwork inprogress
Azman HKL: Earthwork
Azman HKL: Zone 1D. Pile cap inprogress
Azman HKL: Pile cap
Azman HKL: Size ngam kah?
Joseph Wong KH: 100mm diameter for pump sump 5
+60 14-677 8476: Ada Elbow terus tu. Susah pasang formwork bossku.
+60 14-677 8476: Dismantle formwork pun susah tu bossku.😅
+60 14-677 8476: Azman. Ada minta surveyor ambil level kah? Level beam undernet dan drain level?
+60 14-677 8476: Patut kita minta surveyor height of the beam, slab, and external drainage, baru kita boleh pasang pipe sleeve utk ke parit luar.
+60 14-677 8476: Ini drawing saja. Actual on site mau minta level sama surveyor bah
Azman HKL: Itu level sda ada di site. Kalau maw boleh panggil surveyor. Dia ada letak reference on site untuk subcon pasang wall dan slab. Kena tarik sendiri dari itu refences.
+60 14-677 8476: Ok yg penting pihak contractor bertanggung jawab jika ada salah level nanti.😅🤣
Azman HKL: Ada references point tu bossku di site. Semua subcon refer tu level.
Azman HKL: NSC kalau perlu bantuan surveyor boleh request. Surveyor ada di site juga boleh kasi reference point.
+60 14-677 8476: X jadi pasang. Kira punya kira pipe bawa dari parit lagi.🤣🤣🤣🤣🤣🤣
+60 14-677 8476: Mau panetrat juga beam ground floor🤣🤣🤣🤣
NSC GROUP
Azman HKL: Basement wall inprogress
Azman HKL: Wall formwork done dismantled so pipe sleeves for M&E services to install.
Azman HKL: Morning. @Joseph Wong KH when will your worker come to install pipe sleeve?