Monday, December 12, 2022

13 DEC 22 HKL

SITE GROUP

Kadapi: Dart/Walker, smoke detector lagi blum pasang.
Liko: H/6-7

Liko: G/6-7
Liko: @Kadapi J. @Azman HKL .. 2 point untuk Smoke detector sudah siap dipasang.




NSC GROUP

Azman HKL: Site progress. 13/12/2022
4th floor slab. Conduit installation inprogress.
Azman HKL:Slab rebar and conduit work inprogress

Azman HKL:Zone 2, earthwork and hacking in progress

Azman HKL:Basement Zone 1D pile cap earthwork inprogress

Azman HKL:M&E item inspection with consultant.

Lo.W.H (HKL-Site Engineer): @Azman HKL @Joseph Wong KH @Edwin 013
Edwin: The information received was casting till grid line 2. Why suddenly 3 ?
Raymond Chong.Y.F (HKL P. Manager): @Edwin 013 can please arrange? Sudden changed of plan
Raymond Chong.Y.F (HKL P. Manager): Sorry for that
Edwin: Ok. We will arrange to fix the pipe sleeve asap.

Azman HKL: @Edwin 013 @Joseph Wong KH your soil and waste pipe sleeve at wall. And sump pump outlet pipe sleeve.

Azman HKL: M&E item inspection done with approval. 👌

Joseph Wong: @Azman HKL  to inform manhole 1 pipe sleeves location.
Azman HKL: @Joseph Wong KH Next time mark on site so other subcon will know there is item to install.
Joseph Wong: Noted, will do.

Joseph Wong: Manhole 2 Pipe sleeves location



 