SITE GROUP
photos sent by 012-8433877
NSC GROUP
Azman HKL: Site progress. 9/12/2022
4th floor. Slab formwork & beam rebar inprogress
Azman HKL: 3rd floor column inprogress
Azman HKL: Basement watertank area done casting
Azman HKL: Pile cap area, earthwork inprogress
Azman HKL: Zone 2 area. Earthwork inprogress.
Azman HKL: Morning. 4th floor slab casting will postponed to 13/12/2022. Tuesday. Please be informed.