Thursday, December 8, 2022

09 DEC 22 HKL

SITE GROUP
photos sent by 012-8433877




NSC GROUP
Azman HKL: Site progress. 9/12/2022
4th floor. Slab formwork & beam rebar inprogress
Azman HKL: 3rd floor column inprogress

Azman HKL: Basement watertank area done casting

Azman HKL: Pile cap area, earthwork inprogress

Azman HKL:  Zone 2 area. Earthwork inprogress.

Azman HKL:  Morning. 4th floor slab casting will postponed to 13/12/2022. Tuesday. Please be informed.



 