Site progress. 10/11/2022 2nd floor. Formwork and beam in progress
2nd floor slab
2nd floor column
L/6 pile cap
K/9 & L6 pile cap
Basement watertank. Pump sump.
Installing conduit pipe inside column. F/6, G/6, H/6.
2 nd flr
Site inspection
Site inspection
2nd floor. Next casting plan. F-I/7-11