Site progress. 8/11/2022
Joint inspection with consultant at 2nd floor. Still in progress.
Kadapi: A lot of conduits. Atleast 1 person from dcc stay to ensure no damage on conduits during casting.
Done Inspection for M&E conduit and pipe sleeve procced to cast
Azman: NSCs need to confirm Consultant to stay or not for inspection until work done. Installation still in progress. @LO KEAM @Edwin 013 or else he go back home.
Joseph KH: Not need
Raymond : We are casting the slab tonight ya
6.30pm - Concrete pump at site