Friday, November 4, 2022

05 NOV 22 HKL

SITE GROUP


2nd floor

Basement watertank

Site progress. 5/11/2022

Pile cap K/8, K/6

Basement watertank wall formwork

Pile cap

Azman: NSCs, please double. Check any services at basement level slab. GL: K-L/2-4a.

Azman: Pump sump area. Later we check during rebar installation.

Azman: Dear all. 2nd floor casting will be bring forward to Tuesday, 8/11/2022. NSCs please plan your site installation when bottom rebar is ready. We will inform site progress to this group so we can plan early base on site progress.

2nd floor. Rainy day..

Watertank basement.

Pile cap

 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...