SITE GROUP
2nd floor
Basement watertank
Site progress. 5/11/2022
Pile cap K/8, K/6
Basement watertank wall formwork
Pile cap
Azman: NSCs, please double. Check any services at basement level slab. GL: K-L/2-4a.
Azman: Pump sump area. Later we check during rebar installation.
Azman: Dear all. 2nd floor casting will be bring forward to Tuesday, 8/11/2022. NSCs please plan your site installation when bottom rebar is ready. We will inform site progress to this group so we can plan early base on site progress.
2nd floor. Rainy day..
Watertank basement.
Pile cap