GL: F-I/10-11. Tonight GnB will OT to complete all botom layer bar. NSC, please be ready. We target casting on 26/10/2022.
1st floor, GL: F-I/7-9. Botom layer
GL: F-I/9-10.
Lift pit inspection.
Demi Cerah, King Hong bottom bars completing
Installing Lift Pit wall starter bar.
Dear all, slight changes to our 1st floor casting sequence
1st floor. Column casting sequence. Please take note.
1st floor column, conduit installation inprogress
Site progress: 24/10/2022.
1st floor. GL: F-I/7-11. 1st floor rebar in progress.
Lift pit base in progress
Architech Drawing Dimension
Site progress. 24/10/2022. Lift Pit base. Target casting 25/10/2022. Tomorow Tuesday.
SITE group
Conduit in Column F/6
Conduit in Column G/6
Conduit in column GL: F/5
Conduit in Column G/5
Conduit in column H/6
Conduit in column H/5
1st layer bar at 1st floor