Sunday, October 23, 2022

24 OCT 22 HKL

 

GL: F-I/10-11. Tonight GnB will OT to complete all botom layer bar. NSC, please be ready. We target casting on 26/10/2022.

1st floor, GL: F-I/7-9. Botom layer

GL: F-I/9-10.

Lift pit inspection.


Demi Cerah, King Hong bottom bars completing

Installing Lift Pit wall starter bar.

Dear all, slight changes to our 1st floor casting sequence


1st floor. Column casting sequence. Please take note.

1st floor column, conduit installation inprogress

Site progress: 24/10/2022. 
1st floor. GL: F-I/7-11. 1st floor rebar in progress.


Lift pit base in progress

Architech Drawing Dimension

Site progress. 24/10/2022. Lift Pit base. Target casting 25/10/2022. Tomorow Tuesday.



SITE group

Conduit in Column F/6

Conduit in Column G/6

Conduit in column GL: F/5

Conduit in Column G/5

Conduit in column H/6

Conduit in column H/5

1st layer bar at 1st floor