Ground Floor casting plan.
Basement casting plan
Zone 1A: 11/10/22
Zone 1B: 25/10/22
Zone 1D/a: 30/10/22
Site progress 04/10/2022
9.00am.
GL: K-L/1-4 top bar in progress.. DCC please check site condition if you need to install earthing system.
GL: H-I/5-11,
Escalator pit dimension inspection. @Liaw Ka Pang need your site representative to double check the dimension to confirm.
DCC, our earthing have to be install b 4 top layer of the pilecap bars.
The 1st layer bars almost done. We can install the earthing by today.
GL K-L/1-2. Earthing can install now. Take the reading 1st to conferm the better joint. Tq
GF/GL:F-G/7 mausambung conduit dalam colum saja
Gf colum mall