Saturday, October 1, 2022
01 OCT 22 HKL
DCC & GNB on site discuss sequence of work..
DCC installing conduit for lighting, small power and ELV services.
Site progress. 1/10/2022. Slab ground floor.
GL: F-H/8-11.
1st layer slab in progress.