30 SEPT 22 HKL

Install conduit for small power Mall GF

Site progress. 30/09/2022. Slab ground floor. GL: F-H/8-11. 1st layer in progress. NSCs please take note. Target concrete on monday. Steel installation will continue on saturday and sunday.

GL: I-L/5-6.

GL: J-L/1-5






 

No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...