26 SEPT 22 HKL

 




26/09/2022, 8.40am.
Site progress GL: F-H/5-8
Ground Floor, 
2nd layer steel bar in progress. 
1.DCC - 6workers, intall electrical & Elv system.
2.KH - 3workers, install CW & SW at slab.