Friday, September 30, 2022
30 SEPT 22 HKL
Install conduit for small power Mall GF
Site progress. 30/09/2022. Slab ground floor. GL: F-H/8-11. 1st layer in progress. NSCs please take note. Target concrete on monday. Steel installation will continue on saturday and sunday.
GL: I-L/5-6.
GL: J-L/1-5
Thursday, September 29, 2022
29 SEPT 22 HKL
Site progress. 29/09/2022. 8.20am. Ground floor GL: 8-11/F-H
4.40pm. GL: F-H/8-11. Tonite 1st layer bar.
Night work today fixing ground beam rebar
Wednesday, September 28, 2022
28 SEPT 22 HKL
Mall-Ground Floor slab concrete. GL; F-H/5-8.
Leancon, GL: K-L/5-8, cold water tank & pump room Mall.
Column concrete. GL: H-I/5-6
Est. 28/09/2022 today.
Slab concrete. GL: F-H/8-11
Est. 3/10/2022 Monday.
GL: G-L/1a-4.
H/10 column. Small power..
GL: H-I/5-6 column.
Tuesday, September 27, 2022
27 SEPT 22 HKL
Kadapi : Please check archi detail for the open kiosk. I think its not good idea that cold water supply coming from high level hanging its self.
Please tie up properly to the rebar. It risky during casting. It may move or loss by vibration machine. Tq
Kadapi : Casting started, atleast 1 worker from NSCs stay with just incase of MnE damaged then can rectify on the sport. Tq
M&E Coordination meeting no.01. 27/09/2022, 3.07pm.
M&E item inspection with consultant. GL: F-H/5-8.
Monday, September 26, 2022
Subscribe to:
Posts (Atom)
EGMALL NSC (23 SEPT 2024)
EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...
-
SITE EG MALL [11:28, 14/03/2024] +60 16-880 4632: Jackson.. protruding column can hack to flush wall.. [11:31, 14/03/2024] +60 16-880 4632: ...