Tuesday, July 8, 2025

EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025)


[26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. πŸ‘
[26/6/2025 4:42 PM] +60 17-866 0355: Ok man
[26/6/2025 4:51 PM] Kadapi J. PROMES: Area living room ni @~Leppong
[26/6/2025 4:51 PM] Kadapi J. PROMES: Light point
[26/6/2025 4:51 PM] Kadapi J. PROMES: Unit 1
[26/6/2025 4:57 PM] +60 17-866 0355: Ok bos


EGMALL COORDINATION (20/6/2025)

   EGMALL COORDINATION (20/6/2025)

[20/6/2025 9:12 AM] Azman HKL: Tower B. 9th floor. Request for AC drainage flow test. 9.30am. @Kadapi J. PROMES @~sam . ECOnmech @~WY🫨 please standby during inspection. TQ. πŸ‘




[20/6/2025 10:44 AM] Azman HKL: Ok. Noted. @~s4yamahuk4ya88.gmail.com tolong cek nanti. Kalau ada yang begini tolong kasi pasang bagus dia. Tower B. 9th floor. πŸ‘


EGMALL COORDINATION (19/6/2025)

  EGMALL COORDINATION (19/6/2025)



 [19/6/2025 10:14 AM] Kadapi J. PROMES: @Azman HKL & all NSC's. Level 14 & 15 Tower A. Ceiling in progress. Please finish up all services related above ceiling b 4 ceiling cover to be install. Tq

[19/6/2025 10:20 AM] Azman HKL: Noted. Due to Electrical Busduct and other item, ceiling will start at 15th floor first. I will monitored the installation before ceiling covered. πŸ‘

[19/6/2025 10:55 AM] +60 11-2650 7183: Please prepared RFI for consultant for inspection as well after all works done TQ

EGMALL COORDINATION (18/6/2025)

  EGMALL COORDINATION (18/6/2025)

Tower B. 18th floor. Request for M&E inspection at 2pm. @~sam . M&E site PIC, please standby at site during inspection. TQ.πŸ‘. @~Leppong @~WY🫨 @~zee @HIDAYA KH office Num


EGMALL COORDINATION (17/6/2025)

 EGMALL COORDINATION (17/6/2025)



[17/6/2025 9:57 AM] Kadapi J. PROMES: Apa sdh jadi ni conduit d luar daerah sdh. @Azman HKL @EG MALL Nasri πŸ€”
[17/6/2025 9:59 AM] Kadapi J. PROMES: @~zee ,@~s4yamahuk4ya88.gmail.com πŸ€”πŸ€”πŸ€”
[17/6/2025 10:00 AM] Kadapi J. PROMES: Adjust besi x panggil mne adjust conduit juga kah?
[17/6/2025 10:02 AM] Kadapi J. PROMES: Anyone please reply😑
[17/6/2025 10:02 AM] +60 11-6219 0511: saya turun tuan
[17/6/2025 10:04 AM] +60 12-843 3877: Saya datang


EG MALL NSC ( 30 JUNE 2025)

EG MALL NSC ( 30 JUNE 2025)

7th floor. AHU room site discussion with consultant and ECOnmech.


EG MALL NSC ( 28 JUNE 2025)

   EG MALL NSC ( 28 JUNE 2025)

morning. please install scaffolding at this area since the mobile scaffold can't be used due to site condition. We want to install SW pipes for the site office. @~fc @Jimmy HKL 

[28/6/2025 9:23 AM] HIDAYA KH office Num: gridline 6-7
[28/6/2025 9:24 AM] +60 10-809 0001: Ok @Jimmy HKL atur dia
[28/6/2025 9:25 AM] HIDAYA KH office Num: thank you πŸ™πŸ»
[28/6/2025 9:42 AM] Jimmy HKL: okok

19th floor. Tower A. @~Leppong @~WY🫨 @HIDAYA KH office Num @~zee  tolong cek lagi sebelum konkrit. Konsultan komen itu masih ada paip dan konduit jatuh di dalam beam dan dalam wall. Minta kasi keluar.πŸ‘πŸ‘
[28/6/2025 10:39 AM] HIDAYA KH office Num: okay azman
[28/6/2025 10:39 AM] +60 17-866 0355: Ok man

[28/6/2025 2:56 PM] Azman HKL: @EG MALL ECONMECH Dart yang tadi kita bincang. Minimum AHU requirement. 3m atau 2.7m. πŸ‘
[28/6/2025 2:57 PM] EG MALL ECONMECH Dart: The best is 3m. Klau mau rendah perlu proper design with ac design
[28/6/2025 2:58 PM] EG MALL ECONMECH Dart: Ni ka sebab dorg mau tggi ? ☝🏿
[28/6/2025 2:59 PM] EG MALL Mr Lo: Ini apa macam play ground
[28/6/2025 2:59 PM] EG MALL ECONMECH Dart: Ya





EG MALL NSC ( 26 JUNE 2025)

  EG MALL NSC ( 26 JUNE 2025)

Sape punya scaffolding sini? Tolong kasi buka sekarang, mau pasang floor tiles
[26/6/2025 9:51 AM] +60 12-559 6863: @Azman HKL assist
[26/6/2025 9:52 AM] +60 12-559 6863: L14
[26/6/2025 10:52 AM] +60 12-559 6863: Sudah buka kah?
[26/6/2025 10:54 AM] +60 12-559 6863: L20 Isnin kami akan jalan ceiling, tolong siap semua kerja atas ceiling @Azman HKL sila atur
[26/6/2025 10:55 AM] Azman HKL: Okay.

Jimmy, atur worker buka ini scaffold L14 lift lobby dan back charge Econmech, Azman tolong issue
[26/6/2025 1:14 PM] Jimmy HKL: okay bos
[26/6/2025 1:14 PM] +60 12-559 6863: Sekarang
[26/6/2025 1:22 PM] +60 14-379 2990: Bukan econmech..


[26/6/2025 1:22 PM] +60 14-379 2990: Kami pakai ni bos
[26/6/2025 1:23 PM] +60 12-559 6863: Azman, kamu decide



Angin sangat kuat. minta semua pekerja hati2. Minta periksa semua barang yang mudah terbang..

@Azman HKL minta tolong alih ini bar besi. Kami maw sambung paip di sini. 7th floor. Tower B.
[26/6/2025 2:47 PM] Azman HKL: Ok. Saya minta orang kami pindah dia. Tunggu angin kuat stop dulu.
[26/6/2025 2:47 PM] Azman HKL: Ini tempat saja kan..
[26/6/2025 2:50 PM] Oneil KH: Iyaa
[26/6/2025 2:50 PM] Oneil KH: Okay tq
[26/6/2025 3:47 PM] Azman HKL: To all NSC PIC. Please standby for inspection. Maybe at 4pm. We will call for inspection when  the weather is okay and consultant is ready. @~WY🫨 @Oneil KH @~Leppong @~zee

Any confirmation to seal this hole



Let's go for slab inspection. Consultant on the up..




Please support pipe



EG MALL NSC ( 25 JUNE 2025)

  EG MALL NSC ( 25 JUNE 2025)


[25/6/2025 9:16 AM] Azman HKL: Ground floor hotel lobby need to clear
@Azman HKL arah DCC, MITSUBISHI 
@EG MALL Mr Lo @Jimmy HKL  scaffold kasi pindah
[25/6/2025 9:16 AM] Azman HKL: Minta tolong..πŸ‘

Azman, L20 lift lobby ceiling start Isnin minggu depan, bubut siap semua above ceilin

[25/6/2025 9:41 AM] +60 12-843 3877: Ini DCC punya 
Nanti saya cek kalau tak pakai sudah baru kami tutupπŸ™
[25/6/2025 9:48 AM] +60 12-559 6863: @EG MALL ECONMECH Dart what is the minimum height required for AHU room at 7Mezz floor?
[25/6/2025 9:50 AM] EG MALL ECONMECH Dart: 3m bos
[25/6/2025 9:51 AM] EG MALL ECONMECH Dart: Est la
[25/6/2025 9:51 AM] +60 12-559 6863: Max we can provide at site is not higher than 2700mm
[25/6/2025 9:51 AM] EG MALL ECONMECH Dart: Ohlin
[25/6/2025 9:52 AM] EG MALL ECONMECH Dart: Plumbing pipe lagi above below 8F

[25/6/2025 10:36 AM] EG MALL Mr Lo: @EG MALL ECONMECH Dart @Edwin Chen 013, I share the archi file here.
[25/6/2025 10:42 AM] EG MALL ECONMECH Dart: Email ba lo. D sni pndai hilang ni file
[25/6/2025 10:43 AM] EG MALL Mr Lo: ya bro
[25/6/2025 10:55 AM] +60 14-654 4699: To all ncs , please arrange u workers to do housekeeping after lunch, as today Dato Sri will come to site visit at Level 8 Tower B.. Please Arrange you workers ASAP! Thank u


[25/6/2025 3:00 PM] +60 12-843 3877: Guna
[25/6/2025 3:01 PM] +60 12-559 6863: kerja atas siling DCC sudah siap kah?
[25/6/2025 3:03 PM] +60 12-843 3877: Level?
[25/6/2025 3:06 PM] +60 12-559 6863: L20
[25/6/2025 3:06 PM] +60 12-559 6863: kami mau start ceiling hari Isnin


EG MALL NSC ( 24 JUNE 2025)

 EG MALL NSC ( 24 JUNE 2025)

[24/6/2025 8:33 AM] +60 12-559 6863: @~YoonYK shift today ya
[24/6/2025 8:33 AM] +60 19-821 8251: Will do. πŸ™Œ
[24/6/2025 8:33 AM] +60 12-559 6863: Thanks
[24/6/2025 9:10 AM] +60 12-559 6863: Dear all, today’s weekly subcon meeting postpone to next Tuesday 2pm at Tower B L8 unit 11
[24/6/2025 9:11 AM] +60 10-822 2014: Noted


[24/6/2025 9:26 AM] EG MALL Mr Lo: tolong pindah ni barang
[24/6/2025 9:26 AM] EG MALL Mr Lo: saya ada mahu buat setting out




[24/6/2025 2:37 PM] EG MALL Mr Lo: Kasih lari
[24/6/2025 2:39 PM] EG MALL Mr Lo: @~s4yamahuk4ya88.gmail.com
[24/6/2025 2:40 PM] EG MALL Mr Lo: Jawab le
[24/6/2025 2:45 PM] +60 12-559 6863: @EG MALL Mr Lo this is just few nos why don't get Kahar to shift?
[24/6/2025 2:46 PM] EG MALL Mr Lo: We dont want to be responsible …
[24/6/2025 2:47 PM] EG MALL Mr Lo: Already stated morning why dont want remove no tell
[24/6/2025 2:48 PM] +60 12-559 6863: just shift it, if DCC don't shift today then we wait until tomorrow? or after they shift?
[24/6/2025 2:49 PM] +60 12-559 6863: @~s4yamahuk4ya88.gmail.com kasi atur orang kamu pindah sekarang
[24/6/2025 2:59 PM] +60 12-843 3877: Sedang diuruskan πŸ™
[24/6/2025 2:59 PM] +60 12-559 6863: Ok Man, terima kasih
[24/6/2025 3:07 PM] EG MALL Mr Lo: @~WY🫨 tolong check tu plinth position basement
[24/6/2025 3:07 PM] EG MALL Mr Lo: COW m n e ada sana

[24/6/2025 3:46 PM] +60 12-559 6863: Mantap Man dan terima kasih
[24/6/2025 3:46 PM] +60 12-559 6863: @EG MALL Mr Lo your turn
[24/6/2025 3:47 PM] EG MALL Mr Lo: Ok


EG MALL NSC ( 23 JUNE 2025)



    EG MALL NSC ( 23 JUNE 2025)









@~YoonYK please relocate these materials from Lift lobby L19 as our  ceiling work will commence tomorrow 
Afternoon Mr Raymond, ok will do.

EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. πŸ‘ [26/6/2025 4:...