Friday, May 31, 2024
1 JUN 2024 HKL
NSC GROUP
[08:18, 01/06/2024] Azman HKL: Site progress photo.
1/6/24.
21st floor. Slab plinth in progress
[08:18, 01/06/2024] Azman HKL: 7th floor. TB4. Slab rebar and M&E in progress
[08:18, 01/06/2024] Azman HKL: 7th floor. TB6. Slab/beam formwork and beam rebar in progress
[08:20, 01/06/2024] Azman HKL: 3rd floor. Z8. Slab formwork in progress
[08:21, 01/06/2024] Azman HKL: 16th floor. ST6a. Rebar in progress
[08:25, 01/06/2024] Azman HKL: @EG Mall Shafee minta tolong mau ksi sasar ini ducting aircon mau tatai sempai atas
[08:26, 01/06/2024] Azman HKL: @~WY boleh tolong tgk ni ducting. Boleh adjust dia ka supaya plaster boleh jalan.
[09:24, 01/06/2024] Azman HKL: External MH. MH12 and MH13 connection pipe works in progress.
[09:24, 01/06/2024] Azman HKL: MH13.
[09:50, 01/06/2024] EG MALL Mr Lo: @HIDAYA KH office Num, sepetti mana kamu janji pagi tadi …. tolong ya kasih bagus semua tu pipe yang masuk manhole … kita perlu tinbum secepat mungkin
[09:51, 01/06/2024] HIDAYA KH office Num: iya mr lo. workers saya sana suda tu mh13. lepas tu pegi mh12
[09:52, 01/06/2024] EG MALL Mr Lo: Thanks 🙏 @HIDAYA KH office Num
[10:10, 01/06/2024] Azman HKL: 7th floor. TB4. Conduit installation in progress.
[11:19, 01/06/2024] EG MALL ECONMECH Dart: Morning, info utk kita saja ya
[11:19, 01/06/2024] EG MALL ECONMECH Dart: @Azman HKL tlg save man
[11:33, 01/06/2024] Azman HKL: Ok
Thursday, May 30, 2024
31 MAY 2024 HKL
NSC GROUP
[13:24, 31/05/2024] Azman HKL: Site progress photo.
31/5/24.
21st floor. Plinth in progress.
Wednesday, May 29, 2024
Subscribe to:
Posts (Atom)
EGMALL NSC (23 SEPT 2024)
EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...
-
SITE EG MALL [11:28, 14/03/2024] +60 16-880 4632: Jackson.. protruding column can hack to flush wall.. [11:31, 14/03/2024] +60 16-880 4632: ...