Friday, December 30, 2022
31 DEC 22 HKL
SITE GROUP
Azman HKL: Site progress. 31/12/2022
5th floor M&E services installation in progress
Azman HKL: 5th floor formwork in progress
Azman HKL: Basement zone 2.
Azman HKL: Basement zone 1D. Earthwork in progress
30 DEC 22
Thursday, December 29, 2022
30 DEC 22 HKL
SITE GROUP
Azman HKL: Site progress. 30/12/2022
5th floor. Slab rebar in progress
Azman HKL: 5th floor formwork in progress
Azman HKL: Basement. Zone 2. Earthwork and foundation rebar in progress
Azman HKL: Basement zone 1D. Earthwork in progress.
29 DEC 22
Newer Posts
Older Posts
Home
Subscribe to:
Comments (Atom)
EG MALL SITE DAILY ( 31 JULY 2025)
EG MALL NSC ( 11 MARCH 2025)
EG MALL NSC ( 11 MARCH 2025) [11/3/2025 10:26 AM] +60 16-837 8881: Belum habis naik bata tapi mahu paitong sudah ? 6th floor. Genset roo...
EGMALL NSC ( 22 FEB 2025)
EGMALL NSC ( 22FEB 2025) Tower B. 13th floor. Slab for casting. 13th floor. Slab panel and rebar in progress. 12th floor. Wall rebar and...
EGMALL COORDINATION (8/4/2025)
EGMALL COORDINATION (8/4/2025) 7M. Cooling tower, water tank. Plinth inspection. 7M. Done M&E inspection. Please proceed. @EG MALL Nasri